Self Build New Homes

Attention to Detail is always Important!

Home
Building - Where to Start
Self Build Help
Build A House
Build An Extension
Project Manager
NHBC Builder
House Builder
Sheffield Builders
Latest Site Anouncements
Contact Us
Site Map
About Us
Chapeltown Build 2&4 Beds
2 Bed Build Progress 2
4 Bed Build Progress 1
4 Bed Build Progress 2
4 Bed Build Progress 3
4 Bed Build Progress 4
4 Bed Build Progress 5
4 Bed Build Progress 6
LoundSide Project part1
LoundSide Project part2
LoundSide Project part3
LoundSide Project part4
Slide Show of New Build 1
Slide Show of New Build 2
kitchen Video & Pics
New Homes Videos
New Homes in Chapeltown
New Homes in Sheffield
Finding Info on the Net
Past House Build Projects
Established Homes Built
Build a Recording Studio
Compare iPad Tablets
Download MP3 music

 

LoundSide Build Project part 3

 

(May take several seconds to load)

 

 At this point we install a connection to drains for future plot 3, Storm and Foul runs on 100mm Pea Gravel Bed

 

 

 

Pea Gravel now completely covers Pipework, over 100mm coverage,

after Compacting with a Whacker plate - Backfilling Starts

 

 

 

 Now Backfilled ready for more compacting and then Type 1 Crushed stone to Lay on Geotextile Mat

 

 

 

This Geotextile will stop the Type 1 Crushed stone from washing away under the Block Paving after rain 

Geotextiles are permeable fabrics which have the ability to separate, filter, reinforce, protect, or drain.

 

 

 

 

Looking down last part of Driveway towards Aco Gulley where Garages will stand (behind the Parking Spaces)   

 

 

 

Looking from Plot 3 Drive, Type 1 crushed stone laid ready for roller

 

 

Looking at Curve going round towards the garages, box is for service connections

 

 

Look at Driveway formation from Highway

 

Reverse angle, looking at Driveway formation (Type 1 crushed stone on Geotextile)

 

 

Closer look at Service Ducts, ready for connection

 

Vibrating 1.5 Ton Road Roller now smooths out the Drive ready for next stage 

 

Driveway Construction Stage Video

 

 

Main Road Kerb Concreted in place with one cube of Concrete

 

 

Reverse Angle looking at Road Kerbs on left, and you can just see paving kerbs opposite

 

Paving kerbs taking driveway round to Highway from garages

 

Cables and Pipework now connected ready for backfill (1 gas duct for future use left in place)

 

Service connection areas now jointed up and back filled

 

 

Connection area boxes now gone and back filled

 

Charcoal Soldiers Edging for Block paving set in readt mixed concrete

 

Long Radius of Edging Soldiers for Block Paving

 

 

 

 

 

 

 

 

 

 

 