Chapeltown Build 2&4 Beds
4 Bed New Build Progress
4 Bed Build Progress 2
Chap' 2 Bed Build part2
LoundSide Project part1
LoundSide Project part2
LoundSide Project part3
LoundSide Project part4
Slide Show of New Build 1
Slide Show of New Build 2
kitchen Video & Pics
New Homes Videos
New Homes in Chapeltown
New Homes in Sheffield
Finding Info on the Net
Past House Build Projects
Established Homes Built
Build a Recording Studio
LoundSide Build Project part 2
 

(May take several seconds to load)

 
 
 View from Lane End
 

 
 Internal shot from kitchen to living room
 

 
 
 Shot of stairs from kitchen
 

 
 
Ceilings insulated
 

 
 
 Stud wall at top of stairs with Velux window showing
 

 
 bedroom look at Dormer windows
 

 
 Rear look from outside at Dormer windows
 

 
 External cladding completed
 

 
 Front Elevation look
 

 
 
Rear View
 

 
 
Digging out for Drainage (Note Banksman watches for hidden dangers)
 

 
 Living room Insulation in ceilings between Wooden I-Beams and acoustic Insulation around waste pipes
 

 
 Boarding out! ready to Skim
 

 
 Plaster Boarding around internal doors, showing Electrical first fix
 

 
  
 
Outside, Drainage work- Storm and Foul and Inspection Chamber

 
 
 
 
 
 
 
 
 
 
 
 
 
 

More views of foul Drainage and Storm Drains 
  

 

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Inspection Chamber for Foul Drains

 

 

 

 

 
Initial Storm run in lower trench
Note the Rodding Eye for storm
 
 
 
 
 
 
 
 
 
 
 
 
Initial Storm run in lower trench
Note the Rodding Eye for storm (Running under Foul Man Hole) and Inspection Chamber for Foul
Initial Storm and Foul Drain Runs
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Whacker plate ensures pea gravel cover over drains is well compacted
 

 
 
"Type 1" Crushed Stone goes down next and is also compacted, note Aco Drain gulley with Silt Trap at end of run
 

 
 
Inside Doors fitted (Living room to hall door and French doors to Kitchen)
 

 
Kitchen units started to be fitted
 

 
Glazed Wall units fitted
 

 
 
Bathroom furiture arrives!
 

 
 
Master Bedroom Arched window view from doorway
 

 
 
Front of house with first coat of paint on Door
 

 
 
Formation of Driveway in front of garages (not built yet), also main drainage run at the side from front to back of house
 

 
 
Short Video of Vibrating Whacker Plate compacting the pea gravel covering above drainage run 
 
 
 
Underground Elecric Duct covered by Sand with Hazard tape on a Sand bed,
Any future digs will hit tape and sand before Duct and Electric Cable (Hopefully!)
 

 
Future drive has Perforated Land Drain laid at depth then covered in pea gravel before service ducts are laid on top
 

 
 
Laying Service Ducts above land drain on pea gravel then a light sand bed
 

 

 
 
Service Ducts with draw strings in place over land drain ready to be covered with pea gravel then Type 1
 

 
 
Both front doors fitted
 
 

 
Driveway reduced ready for Type 1 crushed stone
 

 

 

Internal look at Bathroom fit, see shower tray bottom right, wc, bath and sink