|
Example of Program of Works
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Work Schedule Example |
|
|
|
|
|
|
|
|
|
Work Schedule Example |
|
|
|
|
|
|
|
|
|
|
|
Work Schedule Example |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
0 |
|
0 |
|
0 |
|
0 |
|
0 |
|
0 |
|
0 |
|
0 |
|
0 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Preliminary's |
|
Preliminary's |
|
Week Starting Mon |
|
Week Starting Mon |
|
Week Starting Mon |
|
Week Starting Mon |
|
Week Starting Mon |
|
Week Starting Mon |
|
Week Starting Mon |
|
Week Starting Mon |
|
Week Starting Mon |
|
Week Starting Mon |
|
Week Starting Mon |
|
Week Starting Mon |
|
Week Starting Mon |
|
Week Starting Mon |
|
Week Starting Mon |
|
Week Starting Mon |
|
Week Starting Mon |
|
Week Starting Mon |
|
Week Starting Mon |
|
Week Starting Mon |
|
Week Starting Mon |
|
Input Start Date |
|
|
|
|
|
|
|
1-Sep-09 |
|
8-Sep-09 |
|
15-Sep-09 |
|
22-Sep-09 |
|
29-Sep-09 |
|
6-Oct-09 |
|
13-Oct-09 |
|
20-Oct-09 |
|
27-Oct-09 |
|
3-Nov-09 |
|
10-Nov-09 |
|
17-Nov-09 |
|
24-Nov-09 |
|
1-Dec-09 |
|
8-Dec-09 |
|
15-Dec-09 |
|
22-Dec-09 |
|
29-Dec-09 |
|
5-Jan-10 |
|
12-Jan-10 |
|
19-Jan-10 |
|
|
|
|
|
|
|
|
|
Week |
|
Week |
|
Week |
|
Week |
|
Week |
|
Week |
|
Week |
|
Week |
|
Week |
|
Week |
|
Week |
|
Week |
|
Week |
|
Week |
|
Week |
|
Week |
|
Week |
|
Week |
|
Week |
|
Week |
|
Week |
|
|
|
|
|
|
|
|
|
1 |
|
2 |
|
3 |
|
4 |
|
5 |
|
6 |
|
7 |
|
8 |
|
9 |
|
10 |
|
11 |
|
12 |
|
13 |
|
14 |
|
15 |
|
16 |
|
17 |
|
18 |
|
19 |
|
20 |
|
21 |
|
|
|
|
|
|
|
|
|
Materials Delivered |
|
Pour Concrete #2 |
|
|
|
|
|
|
|
|
|
|
|
Fit Ridge Beam |
|
NHBC�S Inspected Roof |
Fit Facia Boards |
|
Fit Slates to Rear Roof |
Fan Holes Cut |
|
Order Plasterboards |
|
Elec& Plumb finish 1st fix |
|
|
|
|
|
|
Tiling |
|
|
|
|
|
|
|
|
|
|
|
NHBC notification |
|
F10 submission |
|
1st Conc pour |
|
Bricky's |
|
Bricky's |
|
|
|
Scaffold Start |
|
2nd lift, Lintol hight |
|
Lintols |
|
Roof Structure Started |
|
Fit Roof insulation |
|
Fire stops (Party wall) |
|
Fit Down Pipes |
|
Plumb 1st fix |
|
Fit Plumbing Tails |
|
Plaster boards Del |
|
Ceiling Plaster Skim |
|
Fit Wall Plaster Boards |
Plaster boarding snags |
|
Elec & Plumbing 2nd |
|
Appliances |
|
Decorating snags |
|
Viewings |
|
|
|
|
|
|
|
CDM consultation |
|
Shuttering |
|
Foundation Blocks |
|
Start from DPC |
|
|
|
1st lift, Window sills |
|
|
|
4th lift,� |
|
Fit Roof Restraint Straps |
|
dormer boarding |
|
Fit Barge Boards |
|
Fit soil & Vent Pipes |
|
Fit Flooring (Both Flrs) |
|
Fit Floor Insulation |
|
PlasterBoard Ceilings |
|
|
|
Gas/Water/Elec/BT |
|
Fit Internal Doors |
|
Fit Baths/Showers cub |
|
Fixtures & Fittings |
|
Landscaping Completed |
|
|
|
|
|
|
|
Architect consultations |
|
Engineer consultations |
|
Start Steel Fixing |
|
brickwork to DPC |
|
Start Blockwork |
|
Fit Grnd Floor Joist/Beams |
Trestle Hight internal |
|
Fit Padstones |
|
Brickwork |
|
Fit Cut ups Cav Closers |
|
Fit Roof Boarding |
|
Order Floor Insulation Bats |
Fit Slates to Front Roof |
|
Fit Internal stud work |
|
Glass Delivery |
|
Path Materials Delivery |
|
Joinery 2nd fix |
|
Decorating |
|
WC/sinks fitted |
|
Fit/Test Boiler |
|
Fit Curtain rails |
|
|
|
|
|
|
|
Drawings |
|
Appoint NHBC |
|
Reinforcement |
|
Commons Delivery |
|
Start Stonework |
|
Block Infilling |
|
Fit Service Boxes |
|
Fit Lintols |
|
|
|
Set Purlins if any |
|
Valley's constructed |
|
Heating pipes B.Boxs |
|
Elec Materials Delivered |
|
Fit initial Pipe runs |
|
Fit Door Frames |
|
Fit Window Frames |
|
Fit Glazing |
|
Order Garage Door |
|
Fit Skirts/Architraves |
|
Radiators mounted |
|
Tiling Completed |
|
Footpaths finished |
|
|
|
Attached House |
|
|
|
Order Stone/Blocks etc |
|
Spoil removal |
|
(Cages) |
|
Sand/Cement Del |
|
|
|
Temporary Flr Boards |
|
Fit Hockey Stick |
|
Fit 1st Floor Joist |
|
Fit 1st floor Restraint straps |
Underside netting |
|
Fit Soil roof vents |
|
Tile or slate dormers |
|
Elec first fix |
|
Fit Drainage outlets |
|
Patios Delivered |
|
|
|
Garage Construction |
Book Painters |
|
Lay Rear Paths |
|
Fit lights/switches/Soc |
|
Fit Taps,toilet seats |
|
Fit Garden Fences |
|
|
|
Program Schedule |
|
|
|
Order Dec Cills/Lintols |
|
Tree removal |
|
Extra Shuttering |
|
Wall ties Delivery |
|
Fit DPC Membrane |
|
Fit Door Templates |
|
Fit Decorative Sills |
|
Internal wall build |
|
Block Infilling |
|
Purlin Positions if any |
|
Inspections |
|
Fit Chimney Vent |
|
Fit initial Cable runs |
|
Stairs Delivery |
|
Window Frames del |
|
Fit Stairs |
|
Order Skirts/Architrave |
|
Wall Plasterboard SkIm |
Order Tiling |
|
Fit Worktops |
|
Garage Doors Fitted |
|
Cleaning |
|
|
|
|
|
|
|
Order Steel Mesh & Bar |
|
Shuttering |
|
Order Service Boxes |
|
Book Scaffold |
|
Oversite Concrete |
|
Fit Wall Insulation |
|
Fit Window Templates |
|
Inspections |
|
restraint straps |
|
Fit Rafters in place |
|
|
|
Fit Rainware |
|
|
|
Fit Alarm Cables/Video/TV |
|
Noggs for Pendants |
|
Fit Glazing |
|
Mark out Drive/paths |
|
Landscape Rear |
|
Fit Kitchen Units |
|
Fit Door Hardware |
|
Fit Laminate Flooring |
|
Dressing |
|
|
|
|
|
|
|
contact Services |
|
Heave protection |
|
Order Sand/Cement/Febmix |
|
Drainage layout |
|
Radon barrier |
|
Fit Floor Insulation |
|
Mullions? |
|
|
|
Cavity Closers Delivery |
|
Slates Delivered |
|
|
|
Aerial fitted |
|
Order Decking for Floors |
Fit Door Cav Closers |
|
1st Paint Windows |
|
|
|
Clear Base around hs |
|
Inspections |
|
Laminate Delivery |
|
Rear Fences mounted |
|
Heating Tested |
|
Final Checks |
|
|
|
|
|
|
|
Fencing? |
|
Inspections |
|
Order Regularised Joist #1&2 |
|
Order Templates |
|
Insulation Delivery |
|
Inspections DPC |
|
|
|
3rd lift, |
|
Roof Materials Del |
|
Drainage Delivery |
|
|
|
Fit Lat & Felt |
|
Flooring Materials del |
|
Order for Paths etc |
|
Plumb Preasure Test |
|
Boxing Pipework |
|
Fit Window Sills |
|
Skirt/Architrave Delivery |
|
Inspections |
|
Electrical Testing complete |
|
Skip for clearance |
|
|
|
|
|
|
|
|
|
Order kicker blocks |
|
Order Hockey Stick/Box |
|
Soil pipes in place |
|
Order Floor 2 I-Beams |
|
|
|
Floor Joist Delivery #2 |
|
Order Cavity Closers |
|
Order Patio Doors |
|
Valley sets |
|
Seal all Cavity's |
|
|
|
|
|
Order Stud Timber |
|
Order Doors+ Front dr+Frm |
Start Access Court Prep |
|
Fit Front Door |
|
Lay Front Paths |
|
WC's/Sinks/Bath Delivery |
Turfing Rear |
|
|
|
|
|
|
|
|
|
|
|
Order drainage |
|
Order Floor I-Beams+Hangers |
|
Order Insulation |
|
Blocks/Stone Delivery |
|
Order Lintols (struc) |
|
Lintols (Struc) Delivery |
|
Order Ridge beam |
|
Order Windows onsite |
|
5th lift Gables cut ups |
|
Cut up's complete |
|
|
|
Fit Lead work |
|
Order Stairs |
|
Paint Facias |
|
Order Door Frames |
|
Window Sills Delivery |
|
Footpath Prep |
|
Order WC's/Sinks/Bath |
Elec 2nd fix Mat Del. |
|
Garage Doors Delivery |
|
|
|
Inspections |
|
|
|
|
|
|
|
Excavate for drainage |
|
Mark Out, Check Position |
|
Order Wall Ties |
|
I-beams delivery |
|
Order Ridge Beams |
|
D�cor Cills Lintols Del |
|
Order PAN Timber |
|
|
|
Order Roof Materials |
|
Fit Restraint Straps |
|
|
|
Order Stairs |
|
Back boxes mounted |
|
Lead work complete |
|
|
|
Final paint Windows |
|
Landscaping Front |
|
Lay Outdoor Cables for Lighting |
Rads Delivered |
|
Boiler Delivery |
|
|
|
Regs/NHBC Final Inspection |
|
|
|
|
|
Fit Drainage |
|
for reinforced strip footings |
|
Soil pipes positioned |
|
Radon Protection DPC's |
|
|
|
Service box Deliivery |
|
|
|
|
|
Order Slates |
|
Order Plumbing Mat's |
|
|
|
|
|
Fit Soffits (enclosed) |
|
Finish all under floor work |
|
Fit Patio Cav Closers |
|
Remove Scaffold |
|
Order Kitchen |
|
Order Laminate |
|
Turf Delivery |
|
Turfing Front Lawn |
|
|
|
|
|
|
|
|
|
|
|
|
|
Excavate Footings |
|
Inspections |
|
|
|
|
|
|
|
|
|
|
|
Pan fitted |
|
Velux positioned |
|
|
|
|
|
|
|
|
|
Fit Patio Doors |
|
Stone Delivery |
|
Order Boiler & RADS |
|
Kitchen Delivery |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Order Sewer & M.Holes pipe |
Dropped Curbs Delivery |
|
Order Electrical, Cable, Boxes |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Order Dropped Curbs |
|
Sewer Pipes Materials Del |
|
Water pipes layed |
|
Sewer connection |
|
|
|
Driveways Started |
|
|
|
|
|
|
|
General |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Garage Prep |
|
Sewerage Connection start |
|
Gas Sleaves layed |
|
Services Connected |
|
|
|
Access Court detail |
|
|
|
|
|
|
|
Site |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Lay Cross Drainage |
|
Electric Sleave layed |
|
Elec/Water/BT/Gas? |
|
Landscaping� |
|
Lay Block Paving |
|
|
|
|
|
|
|
Program Schedule |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Sevice trenches dug |
|
Storm trench dug |
|
Bt Sleave Layed |
|
Garden Fence Delivery |
Sand Bed |
|
Landscaping� |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Inspections |
|
Sewerage trench dug |
|
Inspections |
|
Bndry Fence Delivery |
|
Hardcore Court |
|
Driveways Complete |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Drives and Paths Marked |
|
Sewerage Pipe layed |
|
Services to Detached |
|
Paint Delivered |
|
Whacker Hardcore |
|
Bndry Fence Erection |
|
|
|
|
|
|
� |
|
|
|
|
� |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Storm pipe layed |
|
Order Turf |
|
Driveway Materials Del |
|
Order Bndry Fence |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Inspections |
|
Order Paving/Drive Materials |
Lower Cables in Footpath |
Order Garden Fence |
|
|
|
|
|
|
|
|
�������������� |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Fit Drop Curbs� |
|
|
|
Order for Paths etc |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
�
|
|
|
|